Our Hamburg based customer, Neidhardt Grundbau GmbH, installed the tie backs on two sections of the wall using the overburden method. A KLEMM KR 805-3G rig with flushing head was used to install 130 GEWI grouted 40 / 50 DKS piles, with a total drilling length of 2,188 running meters.
The reinforcement of the entire seawall is expected to cost around 10 million EURO with an estimated completion date in 2023, therefore protecting Westerland and its people against future tidal waves.